This resulted in the Summary Task having a zero (0) length. In a couple of cases, the Summary Task only contained milestone activities. These will need to be removed to successfully load the project into P6.
#Microsoft project vs primavera p6 how to#
But P6 does not know how to interpret Cost Resources Types. Resources of Type Cost with zero Cost / UnitĪ Cost Resource Type in MS Project is the equivalent of an Expense in P6. To check this, identify the Material Resources with a Standard Rate of $0.Įither remove the assignments to this Resource or provide a Standard Rate.Ħ. If a Material type Resource is assigned to a Task at zero (0) Units and Cost it will cause an error. Resources of Type Material with zero Cost / Unit Resources with Tasks Missing Baseline ValuesĪdd the Baseline Start field to the Resource Usage view to check for missing baseline values. Rebaseline those specific activities with roll up to Summary levels where the Summary Tasks are missing dates, too.Ĥ. Adjust either the Project Information Start Date or the activities that start before that date.Īdd the Baseline Start column to the Gantt Chart view and check to see if any of them have a value of NA. To determine if this is an issue, check the Start Date under File / Info against the Start field in the Gantt Chart view.
Project Start Date in Project Information is newer than Start date for the first Task. You may have to do this multiple times, as MS Project does not necessarily delete them all on the first try.Ģ. Use “Group By:” in MS Project to identify and delete the tasks. In addition, P6 does not recognize an activity as “inactive” and will treat it as a live activity, reactivating any links or constraints it has assigned. Although not necessarily a problem during the load, several of the other 6 issues identified were only found in the Inactive Tasks. In MS Project, a task can be marked as “inactive” which basically tells the scheduling tool to ignore it. We identified 7 potential problems that needed to be resolved in the MS Project schedule before it will load successfully in P6. However, during the testing several projects errored out and would not load. At face value, this is basically a “Save As XML” in MS Project and “Import Microsoft XML” from P6 operation.
#Microsoft project vs primavera p6 pdf#
ERROR TROUBLESHOOTING IMPORTING MS PROJECT SCHEDULES INTO P6 ORACLE PRIMAVERA P6 DOWNLOAD THE PDF HEREĪ recent client required several hundred Microsoft Project schedules to be migrated to Primavera P6.